Array ( [ID] => 234688 [~ID] => 234688 [NAME] => FGC UES invests RUB 1 bn in the rehabilitation of Siberia’s largest substation [~NAME] => FGC UES invests RUB 1 bn in the rehabilitation of Siberia’s largest substation [IBLOCK_ID] => 36 [~IBLOCK_ID] => 36 [IBLOCK_SECTION_ID] => [~IBLOCK_SECTION_ID] => [DETAIL_TEXT] =>
FGC UES started upgrading the 1,150 kV Itatskaya Substation in the Krasnoyarsk Territory. This will increase the functional reliability of the largest main substations participating in the delivery of capacity of Siberia’s four power plants: the Sayano-Shushenskaya and Krasnoyarskaya HPPs, the Nazarovskaya and Berezovskaya GRES. 

During the rehabilitation it is planned to replace completely the air circuit breakers of 500 and 1,150 kV outdoor switchgear. This switchgar is the crucial switching equipment of substations designated to connect and disconnect ampere capacity in normal and emergency modes. 

Works will be performed on a step-by-step basis within three years. 2018 saw the commencement of replacement of two 1,150 kV air circuit breakers with gas-insulated ones. In 2019, the Itatskaya will launch the rehabilitation of 500 kV outdoor switchgear, entailing the installation of 22 SF6 circuit breakers manufactured in Russia. These devices are more space-effective, reliable, and easy to operate than air circuit breakers, have a longer time between overhauls and service life of 30+ years. 

The replacement of equipment will allow decommissioning the compressor units of substations and improving the energy efficiency of its operations, reducing the labor input of personnel and the consumption of material resources for equipment maintenance and repair purposes.

The 1,150 kV Itatskaya substation with the installed transformer capacity of 1,002 MVA was commissioned in 1982. The substation ensures that the capacity of HPPs and GRES is delivered to the energy systems of the Altai Territory, the Tomsk and Kemerovo Regions.

[~DETAIL_TEXT] =>
FGC UES started upgrading the 1,150 kV Itatskaya Substation in the Krasnoyarsk Territory. This will increase the functional reliability of the largest main substations participating in the delivery of capacity of Siberia’s four power plants: the Sayano-Shushenskaya and Krasnoyarskaya HPPs, the Nazarovskaya and Berezovskaya GRES. 

During the rehabilitation it is planned to replace completely the air circuit breakers of 500 and 1,150 kV outdoor switchgear. This switchgar is the crucial switching equipment of substations designated to connect and disconnect ampere capacity in normal and emergency modes. 

Works will be performed on a step-by-step basis within three years. 2018 saw the commencement of replacement of two 1,150 kV air circuit breakers with gas-insulated ones. In 2019, the Itatskaya will launch the rehabilitation of 500 kV outdoor switchgear, entailing the installation of 22 SF6 circuit breakers manufactured in Russia. These devices are more space-effective, reliable, and easy to operate than air circuit breakers, have a longer time between overhauls and service life of 30+ years. 

The replacement of equipment will allow decommissioning the compressor units of substations and improving the energy efficiency of its operations, reducing the labor input of personnel and the consumption of material resources for equipment maintenance and repair purposes.

The 1,150 kV Itatskaya substation with the installed transformer capacity of 1,002 MVA was commissioned in 1982. The substation ensures that the capacity of HPPs and GRES is delivered to the energy systems of the Altai Territory, the Tomsk and Kemerovo Regions.

[DETAIL_TEXT_TYPE] => html [~DETAIL_TEXT_TYPE] => html [PREVIEW_TEXT] => FGC UES started upgrading the 1,150 kV Itatskaya Substation in the Krasnoyarsk Territory. This will increase the functional reliability of the largest main substations participating in the delivery of capacity of Siberia’s four power plants: the Sayano-Shushenskaya and Krasnoyarskaya HPPs, the Nazarovskaya and Berezovskaya GRES. [~PREVIEW_TEXT] => FGC UES started upgrading the 1,150 kV Itatskaya Substation in the Krasnoyarsk Territory. This will increase the functional reliability of the largest main substations participating in the delivery of capacity of Siberia’s four power plants: the Sayano-Shushenskaya and Krasnoyarskaya HPPs, the Nazarovskaya and Berezovskaya GRES. [PREVIEW_TEXT_TYPE] => text [~PREVIEW_TEXT_TYPE] => text [DETAIL_PICTURE] => Array ( [ID] => 67217 [TIMESTAMP_X] => 29.12.2018 16:26:00 [MODULE_ID] => iblock [HEIGHT] => 336 [WIDTH] => 505 [FILE_SIZE] => 82372 [CONTENT_TYPE] => image/jpeg [SUBDIR] => iblock/3c9 [FILE_NAME] => 3c986e0a5f11449965cc2547f52a4245.jpg [ORIGINAL_NAME] => 33cb10605db4c34b5072b792dce2e429.jpg [DESCRIPTION] => [OLD_FSK_ID] => [OLD_FSK_ID_ENG] => [HANDLER_ID] => [~src] => [SRC] => /upload/iblock/3c9/3c986e0a5f11449965cc2547f52a4245.jpg ) [~DETAIL_PICTURE] => 67217 [ACTIVE_FROM] => 26.12.2018 [~ACTIVE_FROM] => 26.12.2018 [LIST_PAGE_URL] => /eng/public_relations/news/ [~LIST_PAGE_URL] => /eng/public_relations/news/ [DETAIL_PAGE_URL] => /eng/public_relations/news/?ELEMENT_ID=234688 [~DETAIL_PAGE_URL] => /eng/public_relations/news/?ELEMENT_ID=234688 [LANG_DIR] => /eng/ [~LANG_DIR] => /eng/ [CODE] => [~CODE] => [EXTERNAL_ID] => 234688 [~EXTERNAL_ID] => 234688 [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [IBLOCK_CODE] => eng_news_company [~IBLOCK_CODE] => eng_news_company [IBLOCK_EXTERNAL_ID] => 36 [~IBLOCK_EXTERNAL_ID] => 36 [LID] => en [~LID] => en [NAV_RESULT] => [DISPLAY_ACTIVE_FROM] => 12/26/2018 [FIELDS] => Array ( ) [PROPERTIES] => Array ( [flag_main] => Array ( [ID] => 104 [TIMESTAMP_X] => 2019-02-21 12:46:52 [IBLOCK_ID] => 36 [NAME] => Main news [ACTIVE] => Y [SORT] => 500 [CODE] => flag_main [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 104 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Main news [~DEFAULT_VALUE] => ) [flag_region] => Array ( [ID] => 105 [TIMESTAMP_X] => 2019-02-21 12:46:52 [IBLOCK_ID] => 36 [NAME] => Region news [ACTIVE] => Y [SORT] => 500 [CODE] => flag_region [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 105 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Region news [~DEFAULT_VALUE] => ) [flag_investment] => Array ( [ID] => 106 [TIMESTAMP_X] => 2019-02-21 12:46:52 [IBLOCK_ID] => 36 [NAME] => Investment newa [ACTIVE] => Y [SORT] => 500 [CODE] => flag_investment [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 106 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Investment newa [~DEFAULT_VALUE] => ) [flag_ir_release] => Array ( [ID] => 107 [TIMESTAMP_X] => 2019-02-21 12:46:52 [IBLOCK_ID] => 36 [NAME] => IR release [ACTIVE] => Y [SORT] => 500 [CODE] => flag_ir_release [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 107 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => IR release [~DEFAULT_VALUE] => ) [projects] => Array ( [ID] => 108 [TIMESTAMP_X] => 2019-02-21 12:46:52 [IBLOCK_ID] => 36 [NAME] => Projects [ACTIVE] => Y [SORT] => 500 [CODE] => projects [DEFAULT_VALUE] => [PROPERTY_TYPE] => G [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 108 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Projects [~DEFAULT_VALUE] => ) [mes] => Array ( [ID] => 109 [TIMESTAMP_X] => 2019-02-21 12:46:52 [IBLOCK_ID] => 36 [NAME] => MES [ACTIVE] => Y [SORT] => 500 [CODE] => mes [DEFAULT_VALUE] => [PROPERTY_TYPE] => G [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => Y [XML_ID] => 109 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 73 [WITH_DESCRIPTION] => [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => MES [~DEFAULT_VALUE] => ) [mes_show_contacts] => Array ( [ID] => 110 [TIMESTAMP_X] => 2019-02-21 12:46:52 [IBLOCK_ID] => 36 [NAME] => Show MES contacts [ACTIVE] => Y [SORT] => 500 [CODE] => mes_show_contacts [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 110 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [PROPERTY_VALUE_ID] => 198552 [VALUE] => Yes [DESCRIPTION] => [VALUE_ENUM] => Yes [VALUE_XML_ID] => true [VALUE_ENUM_ID] => 47 [~VALUE] => Yes [~DESCRIPTION] => [~NAME] => Show MES contacts [~DEFAULT_VALUE] => ) [photo_gallery_id] => Array ( [ID] => 111 [TIMESTAMP_X] => 2019-02-21 12:46:52 [IBLOCK_ID] => 36 [NAME] => Photoalbum [ACTIVE] => Y [SORT] => 500 [CODE] => photo_gallery_id [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 111 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Photoalbum [~DEFAULT_VALUE] => ) [photo_gallery_items] => Array ( [ID] => 112 [TIMESTAMP_X] => 2019-02-21 12:46:52 [IBLOCK_ID] => 36 [NAME] => Photo [ACTIVE] => Y [SORT] => 500 [CODE] => photo_gallery_items [DEFAULT_VALUE] => [PROPERTY_TYPE] => E [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 112 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Photo [~DEFAULT_VALUE] => ) ) [DISPLAY_PROPERTIES] => Array ( ) [IBLOCK] => Array ( [ID] => 36 [~ID] => 36 [TIMESTAMP_X] => 21.02.2019 12:46:52 [~TIMESTAMP_X] => 21.02.2019 12:46:52 [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [LID] => en [~LID] => en [CODE] => eng_news_company [~CODE] => eng_news_company [NAME] => News [~NAME] => News [ACTIVE] => Y [~ACTIVE] => Y [SORT] => 500 [~SORT] => 500 [LIST_PAGE_URL] => /eng/public_relations/news/?ID=36 [~LIST_PAGE_URL] => /eng/public_relations/news/?ID=36 [DETAIL_PAGE_URL] => #SITE_DIR#/public_relations/news/?ELEMENT_ID=#ID# [~DETAIL_PAGE_URL] => #SITE_DIR#/public_relations/news/?ELEMENT_ID=#ID# [SECTION_PAGE_URL] => #SITE_DIR#/public_relations/news/?SECTION_ID=#ID# [~SECTION_PAGE_URL] => #SITE_DIR#/public_relations/news/?SECTION_ID=#ID# [PICTURE] => [~PICTURE] => [DESCRIPTION] => [~DESCRIPTION] => [DESCRIPTION_TYPE] => text [~DESCRIPTION_TYPE] => text [RSS_TTL] => 24 [~RSS_TTL] => 24 [RSS_ACTIVE] => N [~RSS_ACTIVE] => N [RSS_FILE_ACTIVE] => N [~RSS_FILE_ACTIVE] => N [RSS_FILE_LIMIT] => 10 [~RSS_FILE_LIMIT] => 10 [RSS_FILE_DAYS] => 7 [~RSS_FILE_DAYS] => 7 [RSS_YANDEX_ACTIVE] => N [~RSS_YANDEX_ACTIVE] => N [XML_ID] => 36 [~XML_ID] => 36 [TMP_ID] => [~TMP_ID] => [INDEX_ELEMENT] => Y [~INDEX_ELEMENT] => Y [INDEX_SECTION] => Y [~INDEX_SECTION] => Y [WORKFLOW] => Y [~WORKFLOW] => Y [BIZPROC] => N [~BIZPROC] => N [SECTION_CHOOSER] => L [~SECTION_CHOOSER] => L [LIST_MODE] => [~LIST_MODE] => [VERSION] => 1 [~VERSION] => 1 [LAST_CONV_ELEMENT] => 0 [~LAST_CONV_ELEMENT] => 0 [SOCNET_GROUP_ID] => [~SOCNET_GROUP_ID] => [EDIT_FILE_BEFORE] => [~EDIT_FILE_BEFORE] => [EDIT_FILE_AFTER] => [~EDIT_FILE_AFTER] => [SECTIONS_NAME] => Разделы [~SECTIONS_NAME] => Разделы [SECTION_NAME] => Раздел [~SECTION_NAME] => Раздел [ELEMENTS_NAME] => Элементы [~ELEMENTS_NAME] => Элементы [ELEMENT_NAME] => Элемент [~ELEMENT_NAME] => Элемент [RIGHTS_MODE] => [~RIGHTS_MODE] => [EXTERNAL_ID] => 36 [~EXTERNAL_ID] => 36 [LANG_DIR] => /eng/ [~LANG_DIR] => /eng/ [SERVER_NAME] => www.fsk-ees.ru [~SERVER_NAME] => www.fsk-ees.ru ) [SECTION] => Array ( [PATH] => Array ( ) ) [SECTION_URL] => )

FGC UES invests RUB 1 bn in the rehabilitation of Siberia’s largest substation

12/26/2018 FGC UES invests RUB 1 bn in the rehabilitation of Siberia’s largest substation
FGC UES started upgrading the 1,150 kV Itatskaya Substation in the Krasnoyarsk Territory. This will increase the functional reliability of the largest main substations participating in the delivery of capacity of Siberia’s four power plants: the Sayano-Shushenskaya and Krasnoyarskaya HPPs, the Nazarovskaya and Berezovskaya GRES. 

During the rehabilitation it is planned to replace completely the air circuit breakers of 500 and 1,150 kV outdoor switchgear. This switchgar is the crucial switching equipment of substations designated to connect and disconnect ampere capacity in normal and emergency modes. 

Works will be performed on a step-by-step basis within three years. 2018 saw the commencement of replacement of two 1,150 kV air circuit breakers with gas-insulated ones. In 2019, the Itatskaya will launch the rehabilitation of 500 kV outdoor switchgear, entailing the installation of 22 SF6 circuit breakers manufactured in Russia. These devices are more space-effective, reliable, and easy to operate than air circuit breakers, have a longer time between overhauls and service life of 30+ years. 

The replacement of equipment will allow decommissioning the compressor units of substations and improving the energy efficiency of its operations, reducing the labor input of personnel and the consumption of material resources for equipment maintenance and repair purposes.

The 1,150 kV Itatskaya substation with the installed transformer capacity of 1,002 MVA was commissioned in 1982. The substation ensures that the capacity of HPPs and GRES is delivered to the energy systems of the Altai Territory, the Tomsk and Kemerovo Regions.


Back to the list