Array ( [ID] => 338568 [~ID] => 338568 [NAME] => Rosseti FGC UES begins final stage of revamping Noginsk 500 kV substation – key link of Moscow energy ring [~NAME] => Rosseti FGC UES begins final stage of revamping Noginsk 500 kV substation – key link of Moscow energy ring [IBLOCK_ID] => 40 [~IBLOCK_ID] => 40 [IBLOCK_SECTION_ID] => [~IBLOCK_SECTION_ID] => [DETAIL_TEXT] =>

Before end of 2022, Rosseti FGC UES (FGC UES, PJSC) will finish installing the main equipment, including power transformers with total capacity of 700 MVA, in the third stage of the comprehensive upgrade of Noginsk 500 kV substation, the main power center for the eastern part of the Moscow agglomeration. Factoring in the work done earlier, the substation will raise its capacity more than twofold: from 1050 to 2200 MVA. The project will improve the reliability of the capital's power system and promote further conditions for development of the Moscow suburbs. The total volume of investments by Rosseti FGC UES is 13.7 bn rubles.

The equipment is placed in enclosed rooms, which ensures protection from environmental effects, considerably lengthens its service, enhances reliability and safety of operation. With gas-insulated switchgears (GIS), the substation's footprint will shrink by 30%.

In the third stage of the upgrade, 110 kV GIS and power equipment with total capacity of 700 MVA will be installed and tunnels for cable lines will be routed. Earlier, basic substation buildings were erected, 220 kV and 500 kV GIS were mounted, and new autotransformers with total capacity of 1500 MVA were installed to their places in enclosed chambers. 

The work is conducted with facility running without any limitations in power supply to the consumers. At the final stage of the upgrade, after 6 kV and 10 kV cable lines are rerouted to the new site, the old equipment will be dismantled. 

Noginsk 500 kV substation is part of the 500 kV Moscow energy ring, which comprises nine power centers and 376 km of transmission lines. The ring topology of power supply for large agglomerations is known as the most reliable one: if one of the links fails, the power can be supplied from other sources.

Also, the facility releases the power of Shatura TPP and provides electricity to Bogorodsky urban district of the Moscow region, where about 215k people live and where big industrial productions are located (Akrikhin pharmaceuticals enterprise, Enegrokabel factory, Noginsk construction products plant, Noginsk agricultural complex, etc.). 

[~DETAIL_TEXT] =>

Before end of 2022, Rosseti FGC UES (FGC UES, PJSC) will finish installing the main equipment, including power transformers with total capacity of 700 MVA, in the third stage of the comprehensive upgrade of Noginsk 500 kV substation, the main power center for the eastern part of the Moscow agglomeration. Factoring in the work done earlier, the substation will raise its capacity more than twofold: from 1050 to 2200 MVA. The project will improve the reliability of the capital's power system and promote further conditions for development of the Moscow suburbs. The total volume of investments by Rosseti FGC UES is 13.7 bn rubles.

The equipment is placed in enclosed rooms, which ensures protection from environmental effects, considerably lengthens its service, enhances reliability and safety of operation. With gas-insulated switchgears (GIS), the substation's footprint will shrink by 30%.

In the third stage of the upgrade, 110 kV GIS and power equipment with total capacity of 700 MVA will be installed and tunnels for cable lines will be routed. Earlier, basic substation buildings were erected, 220 kV and 500 kV GIS were mounted, and new autotransformers with total capacity of 1500 MVA were installed to their places in enclosed chambers. 

The work is conducted with facility running without any limitations in power supply to the consumers. At the final stage of the upgrade, after 6 kV and 10 kV cable lines are rerouted to the new site, the old equipment will be dismantled. 

Noginsk 500 kV substation is part of the 500 kV Moscow energy ring, which comprises nine power centers and 376 km of transmission lines. The ring topology of power supply for large agglomerations is known as the most reliable one: if one of the links fails, the power can be supplied from other sources.

Also, the facility releases the power of Shatura TPP and provides electricity to Bogorodsky urban district of the Moscow region, where about 215k people live and where big industrial productions are located (Akrikhin pharmaceuticals enterprise, Enegrokabel factory, Noginsk construction products plant, Noginsk agricultural complex, etc.). 

[DETAIL_TEXT_TYPE] => html [~DETAIL_TEXT_TYPE] => html [PREVIEW_TEXT] => Before end of 2022, Rosseti FGC UES (FGC UES, PJSC) will finish installing the main equipment, including power transformers with total capacity of 700 MVA, in the third stage of the comprehensive upgrade of Noginsk 500 kV substation, the main power center for the eastern part of the Moscow agglomeration. Factoring in the work done earlier, the substation will raise its capacity more than twofold: from 1050 to 2200 MVA. The project will improve the reliability of the capital's power system and promote further conditions for development of the Moscow suburbs. The total volume of investments by Rosseti FGC UES is 13.7 bn rubles. [~PREVIEW_TEXT] => Before end of 2022, Rosseti FGC UES (FGC UES, PJSC) will finish installing the main equipment, including power transformers with total capacity of 700 MVA, in the third stage of the comprehensive upgrade of Noginsk 500 kV substation, the main power center for the eastern part of the Moscow agglomeration. Factoring in the work done earlier, the substation will raise its capacity more than twofold: from 1050 to 2200 MVA. The project will improve the reliability of the capital's power system and promote further conditions for development of the Moscow suburbs. The total volume of investments by Rosseti FGC UES is 13.7 bn rubles. [PREVIEW_TEXT_TYPE] => text [~PREVIEW_TEXT_TYPE] => text [DETAIL_PICTURE] => Array ( [ID] => 166647 [TIMESTAMP_X] => 07/17/2020 02:50:04 pm [MODULE_ID] => iblock [HEIGHT] => 336 [WIDTH] => 505 [FILE_SIZE] => 66687 [CONTENT_TYPE] => image/jpeg [SUBDIR] => iblock/844 [FILE_NAME] => 844c8faa5782994ca182a5aafaca2c01.jpg [ORIGINAL_NAME] => b938c75ebf3319548f5c60f1ccb53437.jpg [DESCRIPTION] => [HANDLER_ID] => [EXTERNAL_ID] => 2f7dfc67bda19c374c9137eb027bc031 [~src] => [SRC] => /upload/iblock/844/844c8faa5782994ca182a5aafaca2c01.jpg [UNSAFE_SRC] => /upload/iblock/844/844c8faa5782994ca182a5aafaca2c01.jpg [SAFE_SRC] => /upload/iblock/844/844c8faa5782994ca182a5aafaca2c01.jpg [ALT] => Rosseti FGC UES begins final stage of revamping Noginsk 500 kV substation – key link of Moscow energy ring [TITLE] => Rosseti FGC UES begins final stage of revamping Noginsk 500 kV substation – key link of Moscow energy ring ) [~DETAIL_PICTURE] => 166647 [TIMESTAMP_X] => 07/17/2020 02:50:04 pm [~TIMESTAMP_X] => 07/17/2020 02:50:04 pm [ACTIVE_FROM] => 07/13/2020 02:49:00 pm [~ACTIVE_FROM] => 07/13/2020 02:49:00 pm [LIST_PAGE_URL] => /eng/public_relations/news/ [~LIST_PAGE_URL] => /eng/public_relations/news/ [DETAIL_PAGE_URL] => /eng/public_relations/news/?ELEMENT_ID=338568 [~DETAIL_PAGE_URL] => /eng/public_relations/news/?ELEMENT_ID=338568 [LANG_DIR] => /eng/ [~LANG_DIR] => /eng/ [CODE] => [~CODE] => [EXTERNAL_ID] => 338568 [~EXTERNAL_ID] => 338568 [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [IBLOCK_CODE] => eng_news_company [~IBLOCK_CODE] => eng_news_company [IBLOCK_EXTERNAL_ID] => 36 [~IBLOCK_EXTERNAL_ID] => 36 [LID] => en [~LID] => en [NAV_RESULT] => [DISPLAY_ACTIVE_FROM] => 07/13/2020 [IPROPERTY_VALUES] => Array ( ) [FIELDS] => Array ( ) [PROPERTIES] => Array ( [flag_main] => Array ( [ID] => 86 [TIMESTAMP_X] => 2019-07-29 10:51:17 [IBLOCK_ID] => 40 [NAME] => Main news [ACTIVE] => Y [SORT] => 500 [CODE] => flag_main [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 104 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Main news [~DEFAULT_VALUE] => ) [flag_region] => Array ( [ID] => 87 [TIMESTAMP_X] => 2019-07-29 10:51:17 [IBLOCK_ID] => 40 [NAME] => Region news [ACTIVE] => Y [SORT] => 500 [CODE] => flag_region [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 105 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Region news [~DEFAULT_VALUE] => ) [flag_investment] => Array ( [ID] => 88 [TIMESTAMP_X] => 2019-07-29 10:51:17 [IBLOCK_ID] => 40 [NAME] => Investment newa [ACTIVE] => Y [SORT] => 500 [CODE] => flag_investment [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 106 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Investment newa [~DEFAULT_VALUE] => ) [flag_ir_release] => Array ( [ID] => 89 [TIMESTAMP_X] => 2019-07-29 10:51:17 [IBLOCK_ID] => 40 [NAME] => IR release [ACTIVE] => Y [SORT] => 500 [CODE] => flag_ir_release [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 107 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => IR release [~DEFAULT_VALUE] => ) [projects] => Array ( [ID] => 90 [TIMESTAMP_X] => 2019-07-29 10:51:17 [IBLOCK_ID] => 40 [NAME] => Projects [ACTIVE] => Y [SORT] => 500 [CODE] => projects [DEFAULT_VALUE] => [PROPERTY_TYPE] => G [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 108 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Projects [~DEFAULT_VALUE] => ) [mes] => Array ( [ID] => 91 [TIMESTAMP_X] => 2019-07-29 13:20:49 [IBLOCK_ID] => 40 [NAME] => MES [ACTIVE] => Y [SORT] => 500 [CODE] => mes [DEFAULT_VALUE] => [PROPERTY_TYPE] => G [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => Y [XML_ID] => 109 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 12 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => MES [~DEFAULT_VALUE] => ) [mes_show_contacts] => Array ( [ID] => 92 [TIMESTAMP_X] => 2019-07-29 10:51:17 [IBLOCK_ID] => 40 [NAME] => Show MES contacts [ACTIVE] => Y [SORT] => 500 [CODE] => mes_show_contacts [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 110 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 176455 [VALUE] => Yes [DESCRIPTION] => [VALUE_ENUM] => Yes [VALUE_XML_ID] => true [VALUE_SORT] => 500 [VALUE_ENUM_ID] => 18 [~VALUE] => Yes [~DESCRIPTION] => [~NAME] => Show MES contacts [~DEFAULT_VALUE] => ) [photo_gallery_id] => Array ( [ID] => 93 [TIMESTAMP_X] => 2019-07-29 10:51:17 [IBLOCK_ID] => 40 [NAME] => Photoalbum [ACTIVE] => Y [SORT] => 500 [CODE] => photo_gallery_id [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 111 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Photoalbum [~DEFAULT_VALUE] => ) [photo_gallery_items] => Array ( [ID] => 94 [TIMESTAMP_X] => 2019-07-29 10:51:17 [IBLOCK_ID] => 40 [NAME] => Photo [ACTIVE] => Y [SORT] => 500 [CODE] => photo_gallery_items [DEFAULT_VALUE] => [PROPERTY_TYPE] => E [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 112 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Photo [~DEFAULT_VALUE] => ) ) [DISPLAY_PROPERTIES] => Array ( ) [IBLOCK] => Array ( [ID] => 40 [~ID] => 40 [TIMESTAMP_X] => 08/03/2019 01:05:39 pm [~TIMESTAMP_X] => 08/03/2019 01:05:39 pm [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [LID] => en [~LID] => en [CODE] => eng_news_company [~CODE] => eng_news_company [NAME] => News [~NAME] => News [ACTIVE] => Y [~ACTIVE] => Y [SORT] => 500 [~SORT] => 500 [LIST_PAGE_URL] => /eng/public_relations/news/?ID=40 [~LIST_PAGE_URL] => /eng/public_relations/news/?ID=40 [DETAIL_PAGE_URL] => #SITE_DIR#/public_relations/news/?ELEMENT_ID=#ID# [~DETAIL_PAGE_URL] => #SITE_DIR#/public_relations/news/?ELEMENT_ID=#ID# [SECTION_PAGE_URL] => #SITE_DIR#/public_relations/news/?SECTION_ID=#ID# [~SECTION_PAGE_URL] => #SITE_DIR#/public_relations/news/?SECTION_ID=#ID# [CANONICAL_PAGE_URL] => [~CANONICAL_PAGE_URL] => [PICTURE] => [~PICTURE] => [DESCRIPTION] => [~DESCRIPTION] => [DESCRIPTION_TYPE] => text [~DESCRIPTION_TYPE] => text [RSS_TTL] => 24 [~RSS_TTL] => 24 [RSS_ACTIVE] => Y [~RSS_ACTIVE] => Y [RSS_FILE_ACTIVE] => N [~RSS_FILE_ACTIVE] => N [RSS_FILE_LIMIT] => [~RSS_FILE_LIMIT] => [RSS_FILE_DAYS] => [~RSS_FILE_DAYS] => [RSS_YANDEX_ACTIVE] => N [~RSS_YANDEX_ACTIVE] => N [XML_ID] => 36 [~XML_ID] => 36 [TMP_ID] => [~TMP_ID] => [INDEX_ELEMENT] => Y [~INDEX_ELEMENT] => Y [INDEX_SECTION] => Y [~INDEX_SECTION] => Y [WORKFLOW] => N [~WORKFLOW] => N [BIZPROC] => N [~BIZPROC] => N [SECTION_CHOOSER] => L [~SECTION_CHOOSER] => L [LIST_MODE] => [~LIST_MODE] => [RIGHTS_MODE] => S [~RIGHTS_MODE] => S [SECTION_PROPERTY] => [~SECTION_PROPERTY] => [PROPERTY_INDEX] => [~PROPERTY_INDEX] => [VERSION] => 1 [~VERSION] => 1 [LAST_CONV_ELEMENT] => 0 [~LAST_CONV_ELEMENT] => 0 [SOCNET_GROUP_ID] => [~SOCNET_GROUP_ID] => [EDIT_FILE_BEFORE] => [~EDIT_FILE_BEFORE] => [EDIT_FILE_AFTER] => [~EDIT_FILE_AFTER] => [SECTIONS_NAME] => Разделы [~SECTIONS_NAME] => Разделы [SECTION_NAME] => Раздел [~SECTION_NAME] => Раздел [ELEMENTS_NAME] => Элементы [~ELEMENTS_NAME] => Элементы [ELEMENT_NAME] => Элемент [~ELEMENT_NAME] => Элемент [EXTERNAL_ID] => 36 [~EXTERNAL_ID] => 36 [LANG_DIR] => /eng/ [~LANG_DIR] => /eng/ [SERVER_NAME] => [~SERVER_NAME] => ) [SECTION] => Array ( [PATH] => Array ( ) ) [SECTION_URL] => [META_TAGS] => Array ( [BROWSER_TITLE] => [KEYWORDS] => [DESCRIPTION] => ) )

Rosseti FGC UES begins final stage of revamping Noginsk 500 kV substation – key link of Moscow energy ring

07/13/2020 Rosseti FGC UES begins final stage of revamping Noginsk 500 kV substation – key link of Moscow energy ring

Before end of 2022, Rosseti FGC UES (FGC UES, PJSC) will finish installing the main equipment, including power transformers with total capacity of 700 MVA, in the third stage of the comprehensive upgrade of Noginsk 500 kV substation, the main power center for the eastern part of the Moscow agglomeration. Factoring in the work done earlier, the substation will raise its capacity more than twofold: from 1050 to 2200 MVA. The project will improve the reliability of the capital's power system and promote further conditions for development of the Moscow suburbs. The total volume of investments by Rosseti FGC UES is 13.7 bn rubles.

The equipment is placed in enclosed rooms, which ensures protection from environmental effects, considerably lengthens its service, enhances reliability and safety of operation. With gas-insulated switchgears (GIS), the substation's footprint will shrink by 30%.

In the third stage of the upgrade, 110 kV GIS and power equipment with total capacity of 700 MVA will be installed and tunnels for cable lines will be routed. Earlier, basic substation buildings were erected, 220 kV and 500 kV GIS were mounted, and new autotransformers with total capacity of 1500 MVA were installed to their places in enclosed chambers. 

The work is conducted with facility running without any limitations in power supply to the consumers. At the final stage of the upgrade, after 6 kV and 10 kV cable lines are rerouted to the new site, the old equipment will be dismantled. 

Noginsk 500 kV substation is part of the 500 kV Moscow energy ring, which comprises nine power centers and 376 km of transmission lines. The ring topology of power supply for large agglomerations is known as the most reliable one: if one of the links fails, the power can be supplied from other sources.

Also, the facility releases the power of Shatura TPP and provides electricity to Bogorodsky urban district of the Moscow region, where about 215k people live and where big industrial productions are located (Akrikhin pharmaceuticals enterprise, Enegrokabel factory, Noginsk construction products plant, Noginsk agricultural complex, etc.). 